Photographs Taken 2.14.12

Exterior: The gas "main line" is installed, and the "water main" is in progress.
Interior:  Exterior walls being insulated and dry-walled; partition walls are being installed.
There is now temporary heat in the building.


Photographs Taken 1.31.12

Roof truss/sheathing is complete.  Building is "weathered in."
Mechanical systems being roughed in - gas piping and electrical.


Photographs Taken 1.17.12

Roof system is partially completed - will take several more weeks to complete.
The project is on/or ahead of schedule.


Photographs Taken 1.4.12

Truss assemblies are being placed in position with large crane. 
Winter has arrived, workers facing bitter cold.


Photographs Taken 12.20.11

Interior and exterior wood walls completed.
Exterior wrap going on.




Photographs Taken 12.6.11

“Foggy day on site."
Floor is completely poured, and wall construction is underway.


Photographs Taken 11.22.11

Project is at 9% completion. 
Besides site preparation, the footers, foundation, underground plumbing/electric,
and 22,000 out of 28,000 of the concrete floor is completed.


GROUNDBREAKING CEREMONY
October 21, 2011

 

 

| HOME | MH | ID | PREVENTION | ADMINISTRATION | NEWS | CAREERS | ABOUT US | DONATE | CONTACT US | LINKS |

Send e-mail to Dickinson Web Page Design with questions, updates or comments about this web site.
© 2011 All rights reserved. Dickinson Center, Inc.